Account for task deliverables

  • 1
  • Question
  • Updated 2 months ago
Greetings!

  How do record and account (track, list) for tasks' deliverables in MindManager?
  I want to show for a client relationship between tasks and deliverables within the project.

Thank you.

Photo of Andrey Kazak

Andrey Kazak

  • 253 Posts
  • 21 Reply Likes

Posted 2 months ago

  • 1
Photo of Detlef Huß

Detlef Huß

  • 29 Posts
  • 11 Reply Likes
You may do it via formulas. At the aggregating deliverables insert "[Tasks]=COUNT(Children.Progress)". This counts all direct branches with any status, thus indicating the branch as a task, thus segregating from branches with any other meaning.

Photo of Andrey Kazak

Andrey Kazak

  • 246 Posts
  • 21 Reply Likes
Thank you for the suggestion.
Let try implementing this.
Photo of Nick Duffill

Nick Duffill, Champion

  • 604 Posts
  • 248 Reply Likes
Another option would be to enable Task Rollup on the Deliverables. But Detlef's solution with formulas is cleaner, because Task Rollup will convert Deliverables into tasks themselves, which you may not want.