Dependency between topics in different maps

  • 1
  • Question
  • Updated 4 months ago
HI,
is it possible create a dependency (Eg: finish to start) between topics in two different maps?
I need the job in one project to be completed before I can start an activity in another project.
Photo of Vincenzo Quintani

Vincenzo Quintani

  • 15 Posts
  • 0 Reply Likes

Posted 4 months ago

  • 1
Photo of Andreas Lercher

Andreas Lercher

  • 122 Posts
  • 53 Reply Likes
No.

You could link the basis with map roll up, but you have to create this dependency every time new agaun
Photo of Vincenzo Quintani

Vincenzo Quintani

  • 15 Posts
  • 0 Reply Likes
Thanks Andreas for your feedback. Could you please explain me more what you mean with "link the basis with map roll up?"
Photo of Andreas Lercher

Andreas Lercher

  • 122 Posts
  • 53 Reply Likes
No time yet.
Next week I more time
Photo of Jörg

Jörg

  • 81 Posts
  • 16 Reply Likes
map rool up means create a new map and take the other 2 maps in this version.
By this way you can link them.