Effort field in the tasks. How to modify the value?

  • 1
  • Question
  • Updated 2 months ago
I would like to change the effort of a task. As an example, the duration could be 5 days, but the effort could be 2,5 days, because the resource is also doing something else in paralell
Photo of Pedro Galan

Pedro Galan

  • 12 Posts
  • 1 Reply Like

Posted 2 months ago

  • 1
Photo of Ary Velstra, Expert Trainer

Ary Velstra, Expert Trainer

  • 1627 Posts
  • 243 Reply Likes
Open the task pane
Look at duration and effort
You see a box that is ticked.
Untick it and you can change the effort.

If a resource is only available for eg 50% this can be automatic.
Read the help to find out how.

Photo of Pedro Galan

Pedro Galan

  • 12 Posts
  • 1 Reply Like
Thank you for your quick response. But I do not see any box ticked; which one do you mean?
Photo of Pedro Galan

Pedro Galan

  • 12 Posts
  • 1 Reply Like
I am sorry; I already show the check box. 
Thank you for your support