Gantt view: Hiding non-working hours on 'hour granularity' view level

  • 1
  • Question
  • Updated 4 months ago
  • (Edited)
Hello MindManager community,

Just started to use the MindManager 2020 software and I am trying to utilize the Gantt Pro visualization.
I'm pretty impressed so far, but I cannot seem to find a way to 'hide' the non-working hours.
  • You can set the working hours start time,
  • You can set the amount of working hours. 
But I find the amount of 'white space' of the non-working hours a "waste of space" and cluttering.
Am I missing something or is this functionality not present?

I would just like to show only 1 or 2 hours before/after the working day hours.


Note:
The 'cleanness' of the Workday granularity view, I like most, but I cannot use it as half-day tasks is not possible.





Photo of KaaJee

KaaJee

  • 1 Post
  • 0 Reply Likes
  • Frustrated

Posted 4 months ago

  • 1
Photo of Sia

Sia, MindManager Product Design & Management

  • 242 Posts
  • 56 Reply Likes
Hi KaaJee,

This is not currently available, you can shade them but not hide them.