Hi! Is there a way to implement the full range of topics from a right map into a Gant chartt, without rolling up all task info?

  • 1
  • Question
  • Updated 6 months ago
I only get the topics with a date into the Gantt chart, and I cannot address them to the correct higher level topics. It makes it impossible to follow up the project efficiently, using the Gantt chart. Can anyone help?           
Photo of Simon Knapen

Simon Knapen

  • 1 Post
  • 0 Reply Likes

Posted 6 months ago

  • 1
Photo of Ary Velstra, Expert Trainer

Ary Velstra, Expert Trainer

  • 1615 Posts
  • 242 Reply Likes
Well Ganttcharts are meant for communicating about projects, so the behaviour is correct.

But Ganttcharts are also just a VIEW just as the Schedule view or the Tag view.
If you have all tasktopics listed in one of those, You can drag them to the status you want. eg Kanban style etc.

These are available in MM2019 so download a free 30 day trial, to check if this solves your request


Photo of Nick Duffill

Nick Duffill, Champion

  • 528 Posts
  • 179 Reply Likes
If your project has some tasks with the same title, you could switch on topic numbering higher up in the map, which should give each topic a unique number.