How to compute Task Duration in MM2019

  • 1
  • Question
  • Updated 4 weeks ago
  • (Edited)
Hi there, does anyone know if the Task Effort can be computed from a Task Property/ies? I am trying to Set Effort= Drilling Metres / Drilling_Rate e.g. I have a 100m drill hole and I can drill 20m per day so I want the Effort to be =100/20=5 days.  I want the flexibility to change the Drilling_Rate and have the schedule and Gantt Chart update automatically.  Any ideas?
Photo of Stuart Masters

Stuart Masters

  • 1 Post
  • 0 Reply Likes

Posted 4 weeks ago

  • 1
Photo of Tom

Tom

  • 5 Posts
  • 2 Reply Likes

Hi, this is a very good Question. I could not find a possibility to calculate Task Duration so far although it Looks like an ordinary property. I think Mindjet should add this possibility to include task properties into calculation of properties generally.