How to summarize "actual" workdays of tasks?

  • 1
  • Question
  • Updated 2 years ago
  • (Edited)
        I have assigned tasks for my subtopics. See the screenshot. I would like to know the actual "workdays" ,instead of "duration day". For this sample, actual workdays should be 5, but MM get the result 28.
        Is there a way to solve this? thanks.

 
Photo of Daping

Daping

  • 9 Posts
  • 0 Reply Likes

Posted 2 years ago

  • 1
Photo of Nick Duffill

Nick Duffill, Champion

  • 512 Posts
  • 170 Reply Likes
In File > Options > Task Info, check the box "Show Effort field". You will then see the summarised effort as well as the duration:
Photo of Daping

Daping

  • 9 Posts
  • 0 Reply Likes
Yeah, very helpful.  Thank you very much!