I like to put in my plan that I have to go to a meating, and there do a task for that, so I can see this time slot in my Gantt Chart. But I can only det dayes, and not times ?
If I make something that is duration 1 houre Effort 1 houre then It will show in the start of the day?

Regards
Daniel.
Photo of Daniel Lindegaard

Daniel Lindegaard

  • 6 Posts
  • 0 Reply Likes
  • frustrated

Posted 6 years ago

  • 1
Photo of Esther van Wijngaarden

Esther van Wijngaarden

  • 154 Posts
  • 61 Reply Likes
No, you cannot set a start time on a task.
When you plan tasks in hours in a day, they will start from the begin of a day (or after another task finishes).

There is a differance between tasks and appointments!

When you go to a meeting you can put that in your agenda, for instance Outlook. With the Outlook linker you can have that appointment in your map as well.