Is there any way to allocate and distinguish between material and work resources to tasks so that they can be exported to Microsoft Project? 
Photo of bevangg

bevangg

  • 5 Posts
  • 0 Reply Likes

Posted 3 years ago

  • 1
Photo of aHa!Coaching

aHa!Coaching, Champion

  • 1192 Posts
  • 116 Reply Likes
It depends: all resources from MindManager are exported as Work resources to MS project. However, using a marker (such as '@') you could export all the information from MindManager and then change the '@'-marked resources to Material resources in MS Project?


Is that something you could use?