Overutilized / Underutilized Resources feature

  • 2
  • Question
  • Updated 4 years ago
Hi,

I have 2 questions

1- I'm looking to do a resource analysis to identify which team members are underutilized / overutilized.
We've gone in and set the effort for each of the tasks but when I ask MindManager to run a report on under/overutilized resources, it doesn't take into account the effort for each of the tasks.
Example, If a task duration is 25 days, and I've set the effort as 1 day. When I run the report it will show that the task is at 2,500% every day for 25 days, as opposed to 100% for one day.
How can I solve this issue?



2- When I go into 'Manage Resources' in the task pane bar under resoruces, I am unable to change the availability of the MindJet Tasks resources, even if that resource is myself and I'm logged in. How can I change this?


Thanks for your help in advance.
-Yassen
Photo of Yassen

Yassen

  • 27 Posts
  • 0 Reply Likes

Posted 4 years ago

  • 2
Photo of Yassen

Yassen

  • 27 Posts
  • 0 Reply Likes
Hi,

This feature would really allow us to understand who will be overutilized and when, and increase our efficiency as a team drastically. Help on this would be greatly appreciated.
Thanks in advance.
-Yassen