Project optimization - critical path

  • 4
  • Idea
  • Updated 4 years ago
When you have dependent task (finish-to-start), the startdate of the dependent task is updated when you set the date of the previous task later in time.
But when you set the date of the previous task earlier in time, the date of the dependent task does not change.


I would like an option to start all dependent tasks immediately after the previous tasks, without any delay. So you can optimize the projectduration.
Photo of Esther van Wijngaarden

Esther van Wijngaarden

  • 154 Posts
  • 61 Reply Likes

Posted 6 years ago

  • 4
Photo of Carsten

Carsten

  • 28 Posts
  • 2 Reply Likes
It's actually a pity that till today, there haven't been any response to your idea, Esther. This feature would be very welcomed by myself too and should be actually by logic already be integrated. However, obviously there is some reason on Mindjet side, not to consider anything like that????