Red dotted line in Gantt-chart

  • 1
  • Question
  • Updated 5 months ago
  • (Edited)
Hi,
I have been trying to resolve these red dotted lines as shown in the picture. They appear when I create a dependecy between 2.3.4 and 2.4.2.
These lines appeared before and somehow I removed them, but this time I am at a loss. What am I missing here?

Cheers,
Simon

Edit: a word


Photo of Simon

Simon

  • 12 Posts
  • 0 Reply Likes

Posted 5 months ago

  • 1
Photo of Nick Duffill

Nick Duffill, Champion

  • 605 Posts
  • 248 Reply Likes
The red dependencies show the critical path. Any task connected by red dependencies will cause the project to be late, if it is late itself.

You can turn off the display of the critical path in the Gantt chart options.