Roll up task info without dates,

  • 1
  • Idea
  • Updated 6 years ago
I would like to be able to roll up task info (man hours) from sub-topics to overlaying topic. BUT i do not want to assign absolute dates.

If "Topic A" has thre subtopics B, C and D, and they have 4, 9 and 12 hours allocated in task info, I would want Topic A to read "25 hrs"
Photo of Janne Johansson

Janne Johansson

  • 1 Post
  • 0 Reply Likes

Posted 6 years ago

  • 1
Photo of Michael Deutch

Michael Deutch, Official Rep

  • 438 Posts
  • 75 Reply Likes
Janne,

If you're using the latest build of MindManager 2012, you can go to the File menu, select options and then select Task Info. Then, in the task info page, make sure you check the box that says Show Effort Field.

In you map, you can now add effort to tasks (e.g. 4, 9, 12 hours). These hours will roll up with the other task info, if there is any on the topics.

Let us know if this helps.