Task Effort

  • 1
  • Question
  • Updated 6 years ago
  • Answered
Why am I not able to alter duration & effort of a task that was imported from Mindjet Action?
Photo of Dominique Dejonghe

Dominique Dejonghe

  • 26 Posts
  • 2 Reply Likes

Posted 6 years ago

  • 1
Photo of Brittney Mazzetta

Brittney Mazzetta

  • 1981 Posts
  • 68 Reply Likes
Hi Dominique. Can you be a little more specific as to the issue that you are having? I need to obtain a little more information to better understand the question you are asking. Thank you!
Photo of Dominique Dejonghe

Dominique Dejonghe

  • 26 Posts
  • 2 Reply Likes
Photo of Brittney Mazzetta

Brittney Mazzetta

  • 1981 Posts
  • 68 Reply Likes
Thank you for sending this over. Just to be clear, you are trying to edit this in the Mindjet desktop application?
Photo of Esther van Wijngaarden

Esther van Wijngaarden

  • 154 Posts
  • 61 Reply Likes
In tasks you only have a due date and not a start date, duration or effort.
So that fields can not be synchronised when you import those tasks in Mindjet desktop.

But when you export the task from Mindjet desktop to web tasks, you cannot edit the duration or effort either.

Photo of Dominique Dejonghe

Dominique Dejonghe

  • 26 Posts
  • 2 Reply Likes
Yes, I was wondering if that field corresponded with the 'time estimate' and 'actual time' in the Action section

This conversation is no longer open for comments or replies.