Task Info Roll Up Calcuation is incorrect - Using MM9

  • 1
  • Problem
  • Updated 5 years ago
  • Solved
I cannot get the The Roll up Task Info function to calculate correctly in MM 9. Sub topics have the following task info:
20 Minutes
20 Minutes
40 Minutes

All have the same dates

The rolled up info reports a total of 20 minutes
Photo of Terry O'Hearn

Terry O'Hearn

  • 1 Post
  • 0 Reply Likes

Posted 5 years ago

  • 1
Photo of Alex Gooding

Alex Gooding, Champion

  • 827 Posts
  • 208 Reply Likes
You have to establish a finish-to-start relationship dependency between subtopic A and B, and then between B and C.

This tells MM that the roll-up is sequentially cumulative - otherwise it will assume that the tasks are concurrent and the total time needs to be only as long as the longest individual task.