Tasks dependency and offset

  • 1
  • Question
  • Updated 5 months ago
Hi
I'm a addict user of MindManager for last 15 years now and still looking for new usage.
Now, I'm investigating how to use it as Global Project Portfolio management tool.
One basic question is about dependencies between tasks: in MSProject, we can add an offset or delay between 2 tasks, i.e End to End with an offset of -10 days.
I can't find a solution with existing dependencies in MM2020.

Thanks for your help

Fabrice
Photo of FCR

FCR

  • 12 Posts
  • 2 Reply Likes

Posted 5 months ago

  • 1
Photo of Nick Duffill

Nick Duffill, Champion

  • 601 Posts
  • 245 Reply Likes
Hello Fabrice

Lag on dependencies is not a feature at the moment. The workaround at the moment is to insert a delay task between tasks where dependencies need a lag. However this is more complex if you want a negative lag.