Greetings!

  I see that the Tasks Report command of Gantt Pro doesn't output all tasks, including roll-up topics.
  Is there a way to output the same table, but for all the tasks to CSV or XLS(X)?

Thank you.
Photo of Andrey Kazak

Andrey Kazak

  • 247 Posts
  • 21 Reply Likes

Posted 4 weeks ago

  • 1
Photo of Nick Duffill

Nick Duffill, Champion

  • 604 Posts
  • 248 Reply Likes
The Tasks report does not include summaries (from task roll-up or manually defined summaries) to enable the resulting spreadsheet to have further analysis performed, e.g. adding formulas. If it included summaries, some of the numerical values would be represented twice or more.

There is a separate report for the Summaries, but has slightly different column headings, as resources are not rolled up in summaries. 

To get summaries and tasks in the same report, use the "Grid Report" which will export both summaries and tasks from the grid to the same spreadsheet.
Photo of Andrey Kazak

Andrey Kazak

  • 246 Posts
  • 21 Reply Likes
Got it!