The entered holidays are not displayed in the GANTT diagram.

  • 1
  • Problem
  • Updated 1 year ago
Photo of Urs

Urs

  • 2 Posts
  • 0 Reply Likes

Posted 1 year ago

  • 1
Photo of Ary Velstra, Expert Trainer

Ary Velstra, Expert Trainer

  • 1228 Posts
  • 180 Reply Likes
That depends....

What is the duration of the tasK?
In the Gantt chart it will extend the task across working and holidays like Samstag etc.

If in your example the (rest of the) number of days you scheduled is 6 (six) days, the Gantt would be correct.
Unless that week you displayed is where you have Karfreitag and 2. Ostern. In that case the rest of the duration should be 4 (four) days.
Photo of Ary Velstra, Expert Trainer

Ary Velstra, Expert Trainer

  • 1228 Posts
  • 180 Reply Likes
But even so.... I do think that Mindjet developers could easily give the holidays and weekends a different colour to avoid convusion.
Photo of Urs

Urs

  • 2 Posts
  • 0 Reply Likes
Ok, thanks. This is a good Idea. Greetings, Urs