Working with milestones as trigger or task constraint

  • 1
  • Problem
  • Updated 9 months ago
Hi,

I have the problem, that I have sometimes tasks, that have to start at a specific date.
The tasks before this "fixed" tasks are conneted via FS-dependency.
If one of these predecessors will be finished earlier as planned and I "erase" the buffer between the other tasks the "fixed" task move also.

Because MM did not have task contraints I tried to fix the task via a separate milestone as trigger.

It works with the SS dependency but if I use one of the other dependencies the fixed task get a date range which is one day longer than the duration. Is this normal?
And if I use the FS-dependency and move the buffer from all tasks the dates of trigger changes.


Is there a better way to fix a task.

Thorsten
Photo of Thorsten

Thorsten

  • 18 Posts
  • 3 Reply Likes

Posted 9 months ago

  • 1

Be the first to post a reply!